+92-334-0001334 wasajhelum@gmail.com
Punjab Development Program (PDP)

Jhelum City Infrastructure Upgrade

Improvement of Sewerage, Storm Drainage System, Street Pavements & Allied Infrastructure in North & South Areas of Jhelum City (District Jhelum).

Project Summary

Physical Progress

35.0%

Start Date
12-01-2026
End Date
15-05-2027
0
Project Schemes
0 km
Sewer Network
0
Tube Wells
0 km
Distribution Network

Project Overview & Scope

District Jhelum

11 km

Upgradation

61 km

New Sewerage

3 Nos.

Tube Wells

20 km

Distribution
Sewerage System

Upgradation of Existing: 11 km

New Sewerage Network: 61 km

Total Sewer Network: 72 km (236,160 Rft)

Storm Drainage

Total Drainage: 28,480 Rft (8.7 km)

6'x6': 19,200 Rft

5'x4': 7,280 Rft

2'x2': 1,000 Rft

2'x3': 1,000 Rft

Water Supply

New Tube Wells: 3 Nos.

HDPE Distribution: 62,400 Rft (19-20 km)

Coverage: North & South Jhelum

Disposal & Pavements

Disposal Station (Kotla Faqeer): 10 Cusec x1, 15 Cusec x2

Street Pavements: 190,786 Cft (0.8 M sq.ft)

Up to Date Progress

Item-wise Status
North Zone
WorkLocationCompleted / Total (Rft)Status
RCC Sewer 48" diaCivil Line Road2,300 / 2,300 Completed
RCC Sewer 42" diaTrunk Bazar2,023 / 2,023 Completed
RCC Sewer 18" diaDhok Muqarab1,356 / 2,330 In-Progress
RCC Sewer 15" diaChaudhry Muhallah460 / 1,150 In-Progress
RCC Sewer 12" diaKareem Pura576 / 1,104 In-Progress
RCC Sewer 12" diaChaudhry Muhallah872 / 872 Completed
Storm Water Drain 6'x6'Salman Paras2,220 / 2,220 Completed
Drain 3'x4'Main Bazar220 / 220 Completed
South Zone
WorkLocationCompleted / Total (Rft)Status
RCC Sewer 54" diaCMH Road2,130 / 7,580 In-Progress
RCC Sewer 48" diaChristian Colony Road1,850 / 2,350 In-Progress
RCC Sewer 27" diaEidgah1,352 / 1,352 Completed
RCC Sewer 24" diaKotla Faqir3,704 / 3,704 Completed
RCC Sewer 12" diaRashidabad1,216 / 1,216 Completed
Drain 6'x6'CMH5,900 / 5,900 In-Progress
Disposal StationKotla Faqir60% / 100% In-Progress

Zone-wise Scheme Details

02 Schemes
PDP — North Zone, Jhelum
Status: Work in Progress

Improvement of Sewerage, Storm Drainage, Street Pavements & Allied Infrastructure in North Area of Jhelum City.

Key Works & Costs
  • Disposal Station (Pumps @ 10 Cusec x1, @ 15 Cusec x2)
  • Sewerage System: 164,000 Rft (50 Km)
  • Drainage System: 15,080 Rft (4.6 Km)
  • Water Supply Network (3 Tubewells, 62,400 Rft HDPE)
  • Street Pavements: 98,430 Cft
  • Machinery and Equipment: 25 Nos.
Storm Water Drains Breakdown
Drain SizeLength (Rft)
6' × 6' Drain7,800 Rft
5' × 4' Drain5,280 Rft
2' × 3' Drain1,000 Rft
2' × 2' Drain1,000 Rft
PDP — South Zone, Jhelum
Status: Work in Progress

Improvement of Sewerage, Storm Drainage, Street Pavements & Allied Infrastructure in South Area of Jhelum City.

Key Works & Costs
  • Disposal Station (Kotla Faqeer: Pumps @ 15 Cusec x2, @ 10 Cusec x1)
  • Sewerage System: 72,160 Rft (22 Km)
  • Drainage System: 13,400 Rft (4 Km)
  • Street Pavements: 92,356 Cft
Storm Water Drains Breakdown
Drain SizeLength (Rft)
6' × 6' Drain11,400 Rft
4' × 5' Drain2,000 Rft

Pictorial Evidence

On-Site Progress
Excavator and workers laying RCC Sewer 54 inch dia at Kotla Faqeer
South Zone
RCC Sewer 54" dia at Kotla Faqir

Kotla Faqir, Jhelum

Salman Paras Drain Construction
North Zone
Salman Paras Drain

Size: 6'×6' — Completed

CMH Drain Construction
South Zone
CMH Drain

Size: 6'×6' — Jhelum

Laying of RCC Sewer 48 inch dia at Christian Colony Road
South Zone
Laying of RCC Sewer 48" dia

Christian Colony Road

Pipe Factory Manufacturing
Project Asset
Pipe Factory

Manufacturing On-Site

Disposal Station Construction at Kotla Faqir
South Zone
Disposal Station (Kotla Faqir)

60% complete • Rehabilitation ongoing

Machinery Procurement Details

13 PDP  |  18 Available with WASA  |  31 Total
Sr. Machinery Name Procured under PDP Already Available with WASA Total
1 Suction Machine 02 01 03
2 Jetting Machine 02 01 03
3 Dewatering Set Nil 11 11
4 Manhole Desilting Machine Nil 02 02
5 Dump Truck 02 01 03
6 Excavator 02 Nil 02
7 Tractor Trolley 02 01 03
8 Roller Machine 01 Nil 01
9 Concrete Cutter 01 Nil 01
10 Plate Compactor 01 Nil 01
11 Water Tanker Nil 01 01
Grand Total: 13 18 31

Outcomes of the Project

22 Target Areas

Sanitation conditions will be significantly improved after the completion of the project across the following localities where new sewerage is being laid:

North Zone Areas
GT Road (Nawab Colony) Talian Wala Road (Chak Kasas, Chontra, Kharala) Kala Deo Madina Town Tehsil Road Dhoke Jumma Jadda Civil Line Road Kala Gujran Islam Pura Road Shumali Muhallah
South Zone Areas
Rohtas Road Makhdoom Abad Chittan Kotla Faqir West Colony Mirza Sharif Town New Christian Colony Arsal Town Kantrila Jinnah Colony Saeela
Chat on WhatsApp