+92-334-0001334 wasajhelum@gmail.com
Punjab Development Program (PDP)

Jhelum City Infrastructure Upgrade

Improvement of Sewerage, Storm Drainage System, Street Pavements & Allied Infrastructure in North & South Areas of Jhelum City (District Jhelum).

Project Summary

Project Status

Work in Progress

Physical Progress

44%

Financial Progress

33%

North Zone Contractor
MAZCORP-ELITE-KUZU JV
South Zone Contractor
Al-Riaz Civil Engineering Services (Pvt) Ltd.
Design Consultant & Resident Supervision
M/s NESPAK (Pvt) Ltd.
Start Date
12-01-2026
End Date
15-05-2027

Financial Summary

Rs. in Million
Total Project Cost
Rs. 8,192.953 M
North + South Zones
North Zone Cost
Rs. 4,844.847 M
ADP Sr. No. 2333
South Zone Cost
Rs. 3,348.106 M
ADP Sr. No. 2334
Financial Year Project Allocation Release Utilization % (on Release) % (on Cost)
2025-26North Zone700.000700.000700.000100%14.5%
South Zone900.000900.000900.000100%27%
Total1,600.0001,600.0001,600.000100%20%
2026-27North Zone675.000675.000459.00068%9.5%
South Zone630.000630.000630.000100%19%
Total1,305.0001,305.0001,089.00083%13%
Grand TotalNorth Zone1,375.0001,375.0001,159.00084%24%
South Zone1,530.0001,530.0001,530.000100%46%
Total2,905.0002,905.0002,689.00092%33%

All figures in Rs. Million. Total Project Cost — North Zone: Rs. 4,844.847 M  |  South Zone: Rs. 3,348.106 M  |  Total: Rs. 8,192.953 M.

0
Project Schemes
0 km
Sewer Network
0
Tube Wells
0 km
Distribution Network

Project Overview & Scope

District Jhelum

15 km

Upgradation

76 km

New Sewerage

3 Nos.

Tube Wells

20 km

Distribution
Sewerage System

Upgradation of Existing: 15 km (North)

New Sewerage Network: 76 km (40 km N + 36 km S)

Total Sewer Network: 91 km (298,480 Rft)

Storm Drainage

Total Drainage: 28,480 Rft (8.7 km)

North: 4.7 km  |  South: 4.0 km

6'x6': 19,200 Rft

5'x4': 7,280 Rft

2'x2' & 2'x3': 2,000 Rft

Water Supply

New Tube Wells: 3 Nos. (North)

HDPE Distribution: 62,400 Rft (20 km)

Coverage: North Jhelum

Disposal & Pavements

New Disposal Station (Kotla Faqeer, South): 01 No. — 10 Cusec x1, 15 Cusec x2

Street Pavements: 190,786 Cft (0.8 M sq.ft)

Manhole Covers

Manhole Covers: 2,500 Nos.

HDPE Forcemain

HDPE Forcemain: 2 Nos.

Rehabilitation of Disposal Stations

Rehabilitation of Disposal Station (Sahil Colony, North): 01 No.

Up to Date Progress

Item-wise Status
North Zone
WorkLocationCompleted / Total (Rft)Status
Section 1 — Bagh Mohallah / Civil Line / Naya Muhallah
RCC Sewer 54" diaBagh Mohallah to Civil Line Road664 / 2,200 (30%) In-Progress
RCC Sewer 42" diaCivil Line Road (Iqbal Library – Naya Muhallah)— / 380 Not Started
RCC Sewer 36" diaNaya Muhallah to Muhammadi Chowk1,568 / 4,900 (32%) In-ProgressLaying of sewer pipe in progress
RCC Sewer 36" diaIqbal Library Road731 / 731 (100%) Completed
RCC Sewer 27" diaBagh Muhallah968 / 1,350 (71%) In-Progress
RCC Sewer 24" diaGumbad Wali Masjid— / 700 Not Started
Drain 6'x6'Bagh Muhallah Drain187 / 187 (100%) Completed
Section 2 — Katchery Chowk to Kala Gate
RCC Sewer 54" diaKatchery Chowk to Dhoke Mukkarab— / 2,500 Not Started
RCC Sewer 48" diaDhoke Mukkarab to Dhok Firdous Road— / 2,000 Not Started
RCC Sewer 42" diaDhok Firdous Road to KareemPura— / 2,500 Not Started
RCC Sewer 36" diaKareemPura to Mustaqeem Chowk— / 3,200 Not Started
RCC Sewer 33" diaMustaqeem Chowk to Phallian— / 1,850 Not Started
RCC Sewer 30" diaPhallian to Kala Gate— / 1,750 Not Started
Section 3 — Salman Paras / Nirala Mart
RCC Sewer 48" diaSalman Paras → Railway Road → Shandar Chowk → Nirala Mart776 / 5,053 (15%) In-Progress
RCC Sewer 36" diaNirala Mart to Markhor Chowk— / 4,400 Not Started
RCC Sewer 27" diaNirala Mart to Madrassa Hanfia— / 740 Not Started
RCC Sewer 24" diaMadrassa Hanfia to Qabristan Chowk— / 487 Not Started
Section 4 — Gulshan Colony / Tahlian Wala
RCC Sewer 48" diaGulshan Colony Road to Tahlian Wala Road96 / 3,000 (3%) In-Progress
RCC Sewer 42" diaTahlian Wala Road to Kala Deo— / 4,104 Not Started
RCC Sewer 36" diaKala Deo to Dhok Barkat Ali— / 2,766 Not Started
Section 5 — Jada / PTC / Fauji Mill
RCC Sewer 30" diaJada to PTC— / 3,765 Not Started
RCC Sewer 24" diaPTC to Fauji Mill Ground— / 3,025 Not Started
RCC Sewer 21" diaFauji Mill Ground to ZMC Medical Complex— / 3,025 Not Started
RCC Sewer 18" diaZMC Medical Complex to Rescue 1122— / 2,268 Not Started
RCC Sewer 15" diaRescue 1122 to Mirza Hospital— / 1,690 Not Started
Section 6 — Abbas Pura
RCC Sewer 21" diaAbbas Pura544 / 1,650 (33%) In-Progress
Section 7 — Dhoke Muqarab
RCC Sewer 18" diaDhoke Muqarab1,130 / 1,130 (100%) Completed
RCC Sewer 12" diaDhoke Muqarab1,376 / 6,071 (22%) In-ProgressLaying of sewer pipe in progress
Section 8 — Muhallah Chaudrian
RCC Sewer 18" diaMuhallah Chaudrian490 / 490 (100%) Completed
RCC Sewer 15" diaMuhallah Chaudrian260 / 260 (100%) Completed
RCC Sewer 12" diaMuhallah Chaudrian872 / 872 (100%) Completed
Section 9 — 15 Bridge to Laari Ada
Drain 4'x4'15 Bridge to Laari Ada Drain370 / 4,600 (8%) In-ProgressConstruction of drain in progress
Critical Components
RCC Sewer 48" diaSahil Colony to Shadab Pulley2,300 / 2,300 (100%) CompletedBack filling completed
RCC Sewer 42" diaRiver Road to Chandni Chowk (Trunck Bazar)2,023 / 2,023 (100%) Completed
Drain 3'x4'Chandni Chowk to Shandar Chowk220 / 220 (100%) Completed
Drain 6'x6'Salman Paras to 15 Bridge2,340 / 2,340 (100%) Completed
South Zone
WorkLocationCompleted / Total (Rft)Status
Section 1 — Kotla Faqir DS to Chittan (Main Trunk)
RCC Sewer 54" diaKotla Faqir DS to Jaffer Road3,656 / 7,580 (48%) In-ProgressLaying of sewer pipe in progress
RCC Sewer 48" diaJaffer Road to New Christian Colony4,080 / 4,200 (97%) In-Progress
RCC Sewer 42" diaNew Christian Colony to Ibadat Chowk (Rohtas Road)3,800 / 3,932 (96%) In-Progress
RCC Sewer 36" diaIbadat Chowk (Rohtas Road) to Dera Ghosia Restaurant3,752 / 7,610 (49%) In-Progress
RCC Sewer 30" diaGharmala – Monan Road1,340 / 6,170 (22%) In-Progress
RCC Sewer 27" diaDera Ghosia Restaurant to Chittan995 / 2,730 (36%) In-Progress
Section 2 — Hassanabad
RCC Sewer 27" diaHassanabad to Laari Ada— / 4,100 Not Started
Section 3 — Kayani Street
RCC Sewer 15" diaKayani Street1,023 / 1,023 (100%) Completed
RCC Sewer 12" diaKayani Street194 / 194 (100%) Completed
Section 4 — Bagga / Kotla Faqir
RCC Sewer 15" diaBagga / Kotla Faqir1,425 / 1,425 (100%) Completed
Section 5 — Rasheedabad
RCC Sewer 12" diaRasheedabad1,550 / 1,550 (100%) Completed
Section 6 — RCC Drain, West Colony to MirzaAbad
Drain 6'x6'West Colony to MirzaAbad1,600 / 7,500 (21%) In-ProgressConstruction of drain in progress
Section 7 — Disposal Station Kotla Faqir
Disposal StationKotla Faqir70% / 100% In-ProgressSinking of wells completed; plug (PCC 1:2:4) in progress
Critical Components
RCC Sewer 27" diaJhelum-PD Khan Road to Bagga Village1,557 / 1,557 (100%) CompletedLaying & restoration completed
RCC Sewer 24" diaBagga Village to Saeela Village3,700 / 3,700 (100%) CompletedLaying & restoration completed
Drain 6'x6'River to West Colony5,900 / 5,900 (100%) Completed

Zone-wise Scheme Details

02 Schemes
PDP — North Zone, Jhelum
Status: Work in Progress

Improvement of Sewerage, Storm Drainage, Street Pavements & Allied Infrastructure in North Area of Jhelum City.

Contractor: MAZCORP-ELITE-KUZU JV  |  Consultant: M/s NESPAK (Pvt) Ltd.

ADP Sr. No. 2333

Financial Summary (Rs. in Million)
ParticularsAmount (Rs. M)
Total Cost4,844.847
Expenditure till 30.06.2026699.838
Allocation FY 2026-27675.000
Funds Released FY 2026-27675.000
Utilization FY 2026-27459.000 (68%)
Overall Physical Progress36%
Overall Financial Progress24%
Up-to-Date Progress Remarks
  • Laying of RCC Sewer 4.32 / 55 Km completed & in progress.
  • Construction of RCC Drain 1.2 / 4.7 Km completed & in progress.
  • Design of Tube Wells by NESPAK is in progress.
  • Procurement of Machinery: 16 Units received; 09 remaining (06 Dewatering Sets, 02 Winching Machines, 01 Excavator).
Note: Rs. 1,900 Million demanded vide letter No. 921/DMD/WASA/Jlm/2026 dated 14/11/2026. 80% Physical Progress will be achieved during CFY.
Key Works & Quantities
WorkQuantity
Rehabilitation of Disposal Station (Sahil Colony)01 No.
Sewerage System (New 40 km + Upgradation 15 km)Total 55 Km
Drainage System15,080 Rft / 4.7 Km
Water Supply Network (3 Tubewells, HDPE distribution)62,400 Rft / 20 Km
Street Pavements98,430 Cft
Machinery and Equipment25 Nos
Storm Water Drains Breakdown
Drain SizeLength (Rft)
6' × 6'7,800
5' × 4'5,280
2' × 3'1,000
2' × 2'1,000
Sewer Line Breakdown (Dia-wise)
DiaLength (Rft)
12"47,610
15"12,379
18"15,251
21"12,050
24"14,519
27"7,411
30"13,441
33"9,026
36"8,860
42"7,721
48"7,349
54"3,516
60"4,621
66"144
72"181
Water Supply Distribution (HDPE Pipe)
HDPE PipeLength (Rft)
1"8,400
3"12,000
4"11,000
5"11,000
6"10,000
8"10,000
PDP — South Zone, Jhelum
Status: Work in Progress

Improvement of Sewerage, Storm Drainage, Street Pavements & Allied Infrastructure in South Area of Jhelum City.

Contractor: Al-Riaz Civil Engineering Services (Pvt) Ltd.  |  Consultant: M/s NESPAK (Pvt) Ltd.

ADP Sr. No. 2334

Financial Summary (Rs. in Million)
ParticularsAmount (Rs. M)
Total Cost3,348.106
Expenditure till 30.06.2026899.894
Allocation FY 2026-27630.000
Funds Released FY 2026-27630.000
Utilization FY 2026-27630.000 (100%)
Overall Physical Progress56%
Overall Financial Progress46%
Up-to-Date Progress Remarks
  • Laying of RCC Sewer 4.5 / 36 Km completed & in progress.
  • Construction of RCC Drain 2.5 / 4 Km completed & in progress.
  • Construction of Disposal Station Kotla Faqeer 70% completed & in progress (well sinking completed, plug PCC 1:2:4 in progress).
Note: Rs. 1,700 Million demanded vide letter No. 921/DMD/WASA/Jlm/2026 dated 14/11/2026. 100% Physical Progress will be achieved during CFY.
Key Works & Quantities
WorkQuantity
New Disposal Station Kotla Faqeer (Pumps @ 15 Cusec x2, @ 10 Cusec x1)01 No.
Sewerage System (New)36 Km
Drainage System13,400 Rft / 4.0 Km
Street Pavements92,356 Cft
Storm Water Drains Breakdown
Drain SizeLength (Rft)
6' × 6'11,400
4' × 5'2,000
Sewer Line Breakdown (Dia-wise)
DiaLength (Rft)
12"15,746
15"13,254
18"12,808
21"5,706
24"4,281
27"5,821
30"5,279
33"5,008
36"4,492
42"3,868
48"5,643
54"7,477

Pictorial Evidence

On-Site Progress
Restoration at 24Restoration at 24
South Zone
Restoration at 24" Sewer

Kotla Faqeer Village

Laying of RCC Sewer 54 Laying of RCC Sewer 54
South Zone
Laying of RCC Sewer 54" dia

Kotla Faqir DS to Jaffer Road — In-Progress (3,656 / 7,580 Rft, 48%)

Laying of RCC Sewer 48Laying of RCC Sewer 48
South Zone
Laying of RCC Sewer 48" dia at Jaffar Road, CMH

In-Progress (4,080 / 4,200 Rft — 97%)

Laying of RCC Sewer 42Laying of RCC Sewer 42
South Zone
Laying of RCC Sewer 42" dia at Christian Colony

In-Progress (3,800 / 3,932 Rft — 96%)

Laying of RCC Sewer 36Laying of RCC Sewer 36
North Zone
Laying of RCC Sewer 36" dia at Naya Muhallah

In-Progress (1,568 / 4,900 Rft — 32%)

(6' x 6') RCC Storm Water Drain(6' x 6') RCC Storm Water Drain
South Zone
(6' x 6') RCC Storm Water Drain at Cantt

Construction in progress

Sinking of Wet WellSinking of Wet Well
South Zone
Sinking of Wet Well, Kotla Faqeer Disposal Station

In-Progress (70%) — well sinking completed, plug PCC 1:2:4 in progress

(6' x 6') RCC Storm Water Drain(6' x 6') RCC Storm Water Drain
North Zone
(6' x 6') RCC Storm Water Drain at Bagh Muhallah

Completed (187 / 187 Rft)

RCC Pipe Factory — North ZoneRCC Pipe Factory — North ZoneRCC Pipe Factory — North ZoneRCC Pipe Factory — North Zone
North Zone
RCC Pipe Factory — North Zone

Manufacturing on-site (2,593 pipes up to date)

RCC Pipe Factory — South ZoneRCC Pipe Factory — South ZoneRCC Pipe Factory — South ZoneRCC Pipe Factory — South Zone
South Zone
RCC Pipe Factory — South Zone

Manufacturing on-site (3,349 pipes up to date)

Project Maps

GIS — WASA Jhelum
Proposed Sewerage System in Jhelum
Proposed Sewerage System in Jhelum

Proposed & completed work, PDP-1 WASA Jhelum

Critical Portion (PDP) WASA Jhelum
Critical Portion (PDP) WASA Jhelum

Critical locations of the project

Ongoing PDP Works — North Zone
Ongoing PDP Works — North Zone

Up to date progress

Ongoing PDP Works — South Zone
Ongoing PDP Works — South Zone

Up to date progress

Machinery Procurement Details

25 Total  |  16 Procured  |  09 To Be Procured
Sr. Machinery Name Total Procured To Be Procured
1 Suction Machine 03 03 Nil
2 Jetting Machine 03 03 Nil
3 Dewatering Set (2 Cusec) 06 Nil 06
4 Winching Machine 03 01 02
5 Tractor Trolley 02 02 Nil
6 Excavator 01 Nil 01
7 Solid Waste Dump 02 02 Nil
8 Loader Rikshaw 03 03 Nil
9 Water Bowser 02 02 Nil
Grand Total: 25 16 09

Outcomes of the Project

22 Target Areas

Sanitation conditions will be significantly improved after the completion of the project across the following localities where new sewerage is being laid:

North Zone Areas
GT Road (Nawab Colony) Talian Wala Road (Chak Kasas, Chontra, Kharala) Kala Deo Madina Town Tehsil Road Dhoke Jumma Jadda Civil Line Road Kala Gujran Islam Pura Road Shumali Muhallah
South Zone Areas
Rohtas Road Makhdoom Abad Chittan Kotla Faqir West Colony Mirza Sharif Town New Christian Colony Arsal Town Kantrila Jinnah Colony Saeela